Bomere Heath

Posted on: Fri 6th September, 2019

Start date: November 2018

Practical Completion: January 2020

Units: 7 rented (4 x 2 bedroom house, 1 x 2 bedroom bungalow, 2 x 3 bedroom house), 6 Shared Ownership (2 x 2 bedroom house, 4 x 3 bedroom house)

Date

Details

 
August 2019

General progress - Brickwork plots 7-10 windows now installed /1st fix services progressing 

Photo shows plot 5/6 front elevation

May 2019

General progress - Timber frame erection/ roof tiling /floor screed preparation /drainage

Picture shows plots 1 - 6 Roof being tiled in and brickwork commenced.

April 2019

Plots progressing well

February 2019

Site now set up with welfare accommodation and stoned up for off-road parking

All plots – foundations poured with concrete except plots 9/10