Start date: February 2019

Practical Completion: May 2020

Units: 16 rented (10 x 2 bedroom house, 1 x 2 bedroom bungalow, 5 x 3 bedroom house), 16 Shared Ownership (3 x 2 bedroom house, 13 x 3 bedroom house)

Date

Details

 
August 2019

Plot excavation and damp proof coursing is now underway

Storm drainage outlet formed on adjoining land

Highway drainage installed

Curb race 90% complete

Road stoned up and base tarmac laid

May 2019

Storm drainage outlet formed on adjoining land

Site strip underway and stoning of entrance and compound

April 2019

Storm drainage outlet formed on adjoining land

Site strip underway and stoning of entrance